Fort Worth Fiber — Construction Dashboard

City of Fort Worth · FWF Fiber-to-the-Premises Project · Sprocket Networks, LLC
Data as of: April 22, 2026
Static data

Budget vs. Completion

Budget Spent
$0 $37.6M project budget
Underground Construction Complete
0 mi 278.6 mi

Phase Completion Overview Completed footage vs planned, active phases

Total Completed
Total Planned
Overall Progress
Active Phases
Each row shows completed footage vs planned footage per phase. Click a row for sub-segment detail. ≥75% 50–74% 25–49% 1–24% Not started
Phase footage reflects conduit placement. Fiber installation is tracked separately below.

Project Completion Milestones Quarterly footage targets · current quarter highlighted

Conduit Route Progress

Toggle layers ☑

Construction Pipeline

Weekly Production Rate

Mon–Fri work weeks. Stacked bars: Sunrise prime contract (P1, P3, P5) and Jacqueline direct (P2, P4, P6, P7, P9, P10). Click any bar for the per-tracker-reading audit.

Conduit Placement by Phase

Underground duct installation only — the first of several construction stages required to deliver service. After conduit: fiber pull, splicing, building entry, and final turnup. A phase is not "complete" until every stage is done.
Bar fills left-to-right with conduit ft placed / planned ft. Phases without contractors assigned (TBD) are still on the scope; their bars stay empty until work begins.

Vendor Inventory

Snapshot of conduit, vaults, handholes, and fiber reels currently staged at vendor yards. Each yard refreshes when new photos are forwarded — older sets are replaced. Addresses are pending from field; click any photo to enlarge.
Loading inventory…