Fort Worth Fiber — Construction Dashboard

City of Fort Worth · FWF Fiber-to-the-Premises Project · Sprocket Networks, LLC
Data as of: April 22, 2026
Static data

Budget vs. Completion

Budget Spent
$0 $37.6M project budget
Underground Construction Complete
0 mi 278.6 mi

Phase Completion Overview Completed footage vs full phase scope, active phases

Total Completed
Permitted
Total Scope
Overall Progress
Active Phases
Each row shows completed footage vs full phase scope. Click a row for sub-segment detail. ≥75% 50–74% 25–49% 1–24% Not started
Phase footage reflects conduit placement. Fiber installation is tracked separately below.

Project Completion Milestones Quarterly footage targets · current quarter highlighted

Conduit Route Progress

Toggle layers ☑

Construction Pipeline

Weekly Production Rate

Sun–Sat work weeks (ending Saturday). Stacked bars: Sunrise (P1–P5), Jacqueline (P6, P7, P9, P10), and GAC (P17). All direct contract. Lighter-shaded bars (9/5/25 – 1/9/26) are pre-pipeline estimates. Click any bar for the per-tracker-reading audit.

Conduit Placement by Phase

Underground duct installation only — the first of several construction stages required to deliver service. After conduit: fiber pull, splicing, building entry, and final turnup. A phase is not "complete" until every stage is done.
Bar fills left-to-right with conduit ft placed / permitted ft. Phases without contractors assigned (TBD) are still on the scope; their bars stay empty until work begins.

Vendor Inventory

Snapshot of conduit, vaults, handholes, and fiber reels currently staged at vendor yards. Each yard refreshes when new photos are forwarded — older sets are replaced. Addresses are pending from field; click any photo to enlarge.