Budget vs. Completion
Budget Spent
$0
$37.6M project budget
Underground Construction Complete
0 mi
278.6 mi
Phase Completion Overview Completed footage vs planned, active phases
Total Completed
—
Total Planned
—
Overall Progress
—
Active Phases
—
Each row shows completed footage vs planned footage per phase. Click a row for sub-segment detail.
≥75%
50–74%
25–49%
1–24%
Not started
Phase footage reflects conduit placement. Fiber installation is tracked separately below.
Project Completion Milestones Quarterly footage targets · current quarter highlighted
Construction Pipeline
Weekly Production Rate
Mon–Fri work weeks. Stacked bars: Sunrise prime contract (P1, P3, P5) and
Jacqueline direct (P2, P4, P6, P7, P9, P10). Click any bar for the per-tracker-reading audit.
Conduit Placement by Phase
Underground duct installation only — the first of several construction stages required to deliver service.
After conduit: fiber pull, splicing, building entry, and final turnup. A phase is not "complete" until every stage is done.
Bar fills left-to-right with conduit ft placed / planned ft. Phases without contractors assigned (TBD) are still on the scope; their bars stay empty until work begins.
Vendor Inventory
Snapshot of conduit, vaults, handholes, and fiber reels currently staged at vendor yards. Each yard refreshes when new photos are forwarded — older sets are replaced. Addresses are pending from field; click any photo to enlarge.
Loading inventory…