Budget vs. Completion
Budget Spent
$0
$37.6M project budget
Underground Construction Complete
0 mi
278.6 mi
Phase Completion Overview Completed footage vs full phase scope, active phases
Total Completed
—
Permitted
—
Total Scope
—
Overall Progress
—
Active Phases
—
Each row shows completed footage vs full phase scope. Click a row for sub-segment detail.
≥75%
50–74%
25–49%
1–24%
Not started
Phase footage reflects conduit placement. Fiber installation is tracked separately below.
Project Completion Milestones Quarterly footage targets · current quarter highlighted
Construction Pipeline
Weekly Production Rate
Sun–Sat work weeks (ending Saturday). Stacked bars: Sunrise (P1–P5),
Jacqueline (P6, P7, P9, P10), and GAC (P17). All direct contract.
Lighter-shaded bars (9/5/25 – 1/9/26) are pre-pipeline estimates.
Click any bar for the per-tracker-reading audit.
Conduit Placement by Phase
Underground duct installation only — the first of several construction stages required to deliver service.
After conduit: fiber pull, splicing, building entry, and final turnup. A phase is not "complete" until every stage is done.
Bar fills left-to-right with conduit ft placed / permitted ft. Phases without contractors assigned (TBD) are still on the scope; their bars stay empty until work begins.
Vendor Inventory
Snapshot of conduit, vaults, handholes, and fiber reels currently staged at vendor yards. Each yard refreshes when new photos are forwarded — older sets are replaced. Addresses are pending from field; click any photo to enlarge.
Loading inventory…